We determine which data needs to be transferred over which service between corporate systems and the production system. We design the network boundary, access rules and remote maintenance connections around these flows. We carry out the on-site switch, VLAN and migration work through the Industrial OT network segmentation service. If the owner of access rules, the change log and periodic checks will be requested as evidence in an audit, IT/OT compliance and audit evidence preparation is carried out with our Compliance team.

VLAN

Industrial DMZZones and conduitsOT firewallHistorian replicationSecure remote accessChange window

Need and approach

Why is this service needed?

By defining data flows, we reduce the paths an incident can spread through. The location and contents of the OT DMZ are determined by the plant and the data flow. The owner of each flow is recorded.

01

Will segmentation cut off production data flowing to the ERP?

Required flows are preserved. Depending on the design, an intermediate system in the DMZ and defined protocols can be used instead of a direct connection.

02

Isn’t VLAN separation enough?

VLANs separate broadcast domains, but if routing between them isn’t inspected, they don’t form a security boundary. A stateful firewall is recommended between IT and OT.

03

Do we need to replace our existing switches?

In most cases existing managed switches can be used. The new components needed are usually the firewall at the IT/OT boundary and the DMZ servers.

04

How long does the migration take?

The duration depends on the size of the plant and the maintenance window schedule; it’s stated in the quote. The switch to blocking mode is usually tied to planned shutdowns.

Implementation approach

Map first, then rules

01 / ANALYSIS

Flow discovery

Current communication is mapped through passive traffic analysis and interviews with system owners.

02 / PLAN

Target architecture

Zones, conduits, the DMZ and the rule set are designed.

03 / EXECUTION

Monitoring mode

Rules only log; flows are validated with their owners.

04 / HANDOVER

Final cutover

Blocking mode is enabled during a maintenance shutdown, and documentation is finalized.